Key takeaway: The electrical side is what most often changes the shape of a gas to heat pump conversion, and the deciding document is a load calculation under the National Electrical Code rather than the number on your main breaker. A 100 amp service in a gas heated house frequently passes, because a gas range, a gas water heater and a gas dryer keep the three largest electric loads out of the arithmetic. What pushes the number over is the electric strip heat package inside the air handler, not the compressor. A 10 kilowatt kit draws 41.7 amps at 240 volts and lands on a 60 amp breaker, while a 5 kilowatt kit sized to the real gap above the balance point needs only 30 amps. When the panel will not take it, four moves are available. A service upgrade, a listed load management device, a smaller backup heat package, or dual fuel with the existing furnace as backup and no strip heat at all. Panel work, feeders and service upgrades belong to a licensed electrician. TerraStream Energy does the heating and cooling scope across Maryland with Prince George's County first, runs the Manual J, sizes the heat package to the gap, and hands your electrician the published equipment data so the two scopes get sequenced instead of discovered on install day.
What the Existing Service Tells You
Reading the Panel Before Anyone Quotes
The number stamped on your main breaker is the first fact a gas to heat pump conversion has to live with, and you can go read it tonight without any tools.
Open the panel door. Leave the inner cover alone, that part is an electrician's job. In most residential panels the main breaker sits at the top and carries a number printed right on the handle, 100 or 125 or 150 or 200. That figure is the ampacity of your electrical service, the most current the utility's conductors, your meter and your main breaker are rated to pass continuously. At 240 volts, a 100 amp service is a budget of about 24,000 volt amperes.
Write down two more things while the door is open.
Count the empty spaces along the bus, meaning the slots with no breaker clipped into them. Then look at whether the breakers already in there are full size or the narrow tandem type that squeezes two circuits into one slot, since a panel that is electrically fine can still be physically out of room. The manufacturer's name on the label matters as well. A few panel lines built in the 1960s and 1970s have documented failure histories, and no electrician will add load to one.
Reading the panel is not the calculation. It is the context the calculation starts from, and a homeowner who already knows the service is 100 amps with four free slots can hand that to the first contractor who walks the basement.
The 100 Amp House That Predates Central Cooling
A Maryland house wired for 100 amps before anyone set a condenser in the side yard was never asked to run a compressor and a bank of electric heat strips at the same moment, and closing that gap is what the electrical side of a conversion is for.
Think about the original load. Lights and receptacles, a gas furnace drawing a few amps for its blower and igniter, a gas range, a gas water heater, a gas dryer. Summer cooling meant a window unit or two on whatever receptacle was closest. The whole house might have pulled 40 amps on its worst August afternoon.
Decades added things on top. Central air on a 30 amp circuit in the 1980s. Then a microwave, a dishwasher, a second refrigerator in the garage. Sometimes an electric dryer when the gas one finally quit, and now and then a hot tub that nobody mentions until the electrician traces the circuit.
Age works in your favor here. A gas heated house carries more spare capacity than its panel label suggests, since a gas range, a gas water heater and a gas dryer keep three of the largest electric loads out of the arithmetic entirely. The Energy Information Administration's residential energy survey tracks which fuels households actually use for heating, water heating and cooking, and gas does a lot of that work in Maryland houses of this vintage. So a 100 amp service in a gas house frequently passes a load calculation with a heat pump added. Put an electric range, an electric dryer and a 4,500 watt water heater on the same service and it does not. What the code counts is the connected load, so a 1962 panel in a gas house can pass where a 1998 panel in an all electric house fails.
Why 200 Amp Service Is Not an Automatic Yes
A 200 amp service clears the way for most conversions, and three separate things can still stop the job in a house that has one.
Capacity is the first and the easiest to check. The second is physical space, because a heat pump feeder and an air handler feeder each want two adjacent full size spaces on the bus, and a 200 amp panel stuffed with tandems may have nowhere to land either one. Certain panels accept a listed quad breaker that solves this in four slots' worth of room. Many do not, and the fix becomes a subpanel or a panel change even though the service itself is plenty.
Third is the panel's own condition and listing. A 200 amp meter and service entrance sometimes feed a 150 amp rated loadcenter, which caps the calculation at 150 regardless of what the meter says. Aluminum branch wiring, two neutrals jammed under one lug, corrosion on the bus, a missing grounding electrode conductor, all of it gets looked at when someone adds a 60 amp heat circuit, and all of it can turn a simple breaker addition into a day of work.
Finished basements complicate it in a useful direction. Houses that got a basement subpanel during a remodel often have a convenient place to land the air handler feeder, so long as the feeder serving that subpanel has room for what you are about to hang on it.

The Load Calculation That Decides the Project
How the Code Adds a Heat Pump to an Existing House
Whether your panel takes a heat pump is settled by a load calculation under the National Electrical Code, and for a house that already exists the code includes a method written for exactly this situation.
The code in question is NFPA 70, the National Electrical Code, and the relevant chapter is Article 220. Alongside the standard method it carries an optional calculation for an existing dwelling unit taking on additional load. That version lets the electrician start from the demand the house has actually recorded rather than from an assumed worst case, which is why it so often produces a kinder answer than a spreadsheet built from nameplates alone. Maryland jurisdictions adopt the electrical code through the state building performance standards, and Prince George's County inspects the finished work under its own electrical permit, separate from the mechanical permit on the equipment.
Two pieces of input make the calculation honest. One is twelve months of the home's recorded demand, which the serving utility can supply. Pepco is the electric utility across Prince George's County, so that is the account the data comes from here. The other is a full inventory of everything connected in the house, including the garage refrigerator and whatever is plugged in out on the back patio.
One code rule shapes the outcome more than any other. Article 220 normally treats heating and air conditioning as noncoincident loads, meaning they never run together, so the calculation counts only the larger of the two and ignores the smaller. A heat pump breaks that convenience. When the compressor and the supplemental electric heat are arranged to operate at the same time, which is the normal configuration in a Maryland house, both get counted. Your calculated load grows by the compressor plus the heat strips added together.
What the electrician hands back is a volt ampere total divided by 240 volts, compared against the service rating. Under it, the project is a mechanical job with a couple of new circuits. Over it, you are choosing among the four moves in part four.
Why the Strip Heat Package Drives the Number
The electric heat package inside the air handler is what pushes most calculated loads past the service rating, and the outdoor compressor is a far smaller number than homeowners expect.
Start with the compressor, since that is the part everybody pictures. Its rating plate lists a minimum circuit ampacity and a maximum overcurrent protection, abbreviated MCA and MOCP, and on residential heat pumps in the two to four ton range the MCA commonly lands somewhere in the twenties. Modest. A heat pump moves heat rather than making it, and its electrical draw reflects that.
Electric resistance heat makes heat the hard way. One kilowatt of resistance element produces 3,412 Btu per hour, every time, and a 10 kilowatt heat package therefore draws 41.7 amps at 240 volts. Fixed electric space heating counts as a continuous load, so conductors and the breaker get sized at 125 percent of that, which lands at 52 amps and a 60 amp breaker. Put the compressor and that heat kit together and the conversion has added something in the neighborhood of 64 amps of connected load to a service that may only have 100 to give.
The efficiency difference behind those numbers has a name. COP, the coefficient of performance, is the ratio of heat delivered to electrical energy consumed. Resistance strip heat sits at a COP of 1.0 and cannot do better. Every watt becomes a watt of heat, no more. Compressors run well above that, which is why the Department of Energy describes an air source heat pump as cutting heating electricity use substantially against electric resistance heat. Every kilowatt of strip heat you install is the most expensive heat in the house to run and the piece most likely to force a panel upgrade. A 15 kilowatt kit puts 51,200 Btu per hour of it in your air handler, waiting for a cold morning.
The Circuits a Conversion Adds
The Outdoor Unit Feeder and Its Disconnect
The heat pump outside gets a dedicated two pole 240 volt circuit from the panel and a disconnecting switch on the wall beside it, and both come off the unit's rating plate rather than a rule of thumb.
Conductors get sized to the MCA on the plate. The breaker goes no larger than the MOCP on the same plate, and it is an HACR rated breaker because the load is a motor compressor. Expect a 3 ton heat pump to land on a 30 or 35 amp breaker with 10 AWG copper, while a larger unit moves up from there, so the plate decides and the quote should name the number.
A disconnecting means is a code requirement. Your outdoor unit needs one within sight of it and readily accessible, which in practice means a pull out or a small fused switch screwed to the wall a few feet from the condenser. Code also wants a 125 volt receptacle within 25 feet of the equipment so a technician is not running a cord through a window. From the disconnect to the unit, the whip is liquid tight flexible conduit. A run that crosses the yard underground brings burial depth and conduit type into the conversation, and that is a longer day than a run along a foundation wall.
One more detail has caught plenty of installs since the 2020 code cycle. Recent editions added ground fault protection for outdoor dwelling unit outlets, which swept up heat pump circuits, and the interaction between some equipment and some breakers produced nuisance tripping. Whether your inspector enforces that provision as written, and which breaker the manufacturer's installation instructions call for, are questions the electrician settles with the county before wire goes in the ground.
The Air Handler Feeder and the Heat Package
The indoor unit's feeder exists almost entirely to carry the electric heat, which is how the same air handler model needs a 30 amp circuit in one house and an 80 amp circuit in another.
Blower current is the small part. A variable speed ECM motor draws a handful of amps, and an air handler shipped with no heat kit at all would have an unremarkable feeder. The heat kit is the load.
Each air handler carries a rating plate whose MCA and MOCP change according to which heat kit is installed inside it, and the manufacturer publishes a row per kit in the installation manual. Your electrician needs that row, for the exact model pairing, before sizing anything. One code provision explains the shape of the larger kits. Fixed electric space heating loads above 48 amps have to be subdivided, which is why bigger kits arrive with factory breakers already mounted in the cabinet. A single feeder sized for the whole kit still works, with the subdivision happening inside the box. Past roughly 20 kilowatts it becomes two feeders.
That 120 volt circuit on the old gas furnace does not do this job. It powered a blower and a control board, and it ends up either abandoned or reused for a condensate pump.
Why a Different Heat Kit Means Different Wire
Change the backup heat package after the proposal is signed and you change the breaker, you change the conductor, and sometimes you change the answer to whether the panel works at all.
The table below runs the arithmetic for common kit sizes at 240 volts, with the 125 percent continuous load factor already applied in the breaker column and conductor sizes assuming 75 degree Celsius terminations in copper. Real numbers come off the plate for your specific air handler and kit pairing.
Backup heat package | Heat output | Current at 240 volts | Breaker and conductor the code points to | Feeders to the air handler |
|---|---|---|---|---|
None, gas furnace kept as backup | Supplied by the furnace | Blower only | Existing 120 volt furnace circuit | None added |
5 kilowatt kit | About 17,100 Btu per hour | About 20.8 amps | 30 amp breaker, 10 AWG copper | One |
8 kilowatt kit | About 27,300 Btu per hour | About 33.3 amps | 45 or 50 amp breaker, 8 AWG copper | One |
10 kilowatt kit | About 34,100 Btu per hour | About 41.7 amps | 60 amp breaker, 6 AWG copper | One |
15 kilowatt kit | About 51,200 Btu per hour | About 62.5 amps | 80 amp breaker, 4 AWG copper, load subdivided inside the cabinet | One |
20 kilowatt kit | About 68,200 Btu per hour | About 83.3 amps | Two 60 amp breakers, 6 AWG copper each | Two |
What the backup heat package changes on the electrical side of a conversion
Look at the two ends of that table. A 5 kilowatt kit asks for a 30 amp breaker and a pair of 10 AWG conductors, which fits almost anywhere. Jump to a 20 kilowatt kit and you are asking for two 60 amp breakers and roughly 104 amps of calculated load all by itself, which no 100 amp service will absorb. Same house, same heat pump. The kit selection moved the project from two breakers to a service upgrade.
TerraStream Energy installs Daikin and Goodman equipment, and both manufacturers publish the electrical data kit by kit in the installation manual for each air handler, so the MCA and MOCP for a specific model and kit combination is a printed figure rather than an estimate. That matters at quoting time. An electrician given the model numbers can calculate before anyone orders equipment, instead of sizing a feeder to whatever shows up on the truck.

Four Moves When the Panel Will Not Take It
A Service Upgrade and What the Utility Controls
A service upgrade raises the ceiling for everything the house will ever add, and it is the longest lead item in a conversion because the utility owns the hardware in front of your meter.
The scope on a 100 to 200 amp upgrade reaches past the panel. New service entrance conductors, a new meter socket, a new loadcenter with room to grow, the grounding electrode system brought up to current code, every existing branch circuit moved over and relabeled. Prince George's County requires an electrical permit and an inspection on that work. Your utility then has to disconnect and reconnect, which puts Pepco's schedule inside your project schedule.
Overhead and underground services are different animals. An overhead drop is a day of work plus the utility visit. Underground means trenching from the transformer or the pedestal, and that one gets measured in weeks more often than days.
A conversion that includes a service upgrade costs more than a like for like furnace and air conditioner swap. No point pretending otherwise. TerraStream Energy offers financing through the Palmetto Comfort Plan, a lease option that avoids a large upfront equipment cost, so the mechanical work can proceed without writing a check for the equipment on day one. Keep in mind that an electrician bills his own scope separately, which is why a homeowner planning a conversion with panel work in it wants that number in writing alongside the equipment proposal.
A Load Management Device Instead of More Amps
A listed energy management device holds the house under its service rating by shedding one load when another one calls, and the code recognizes that as an alternative to buying more amps.
Article 750 of the National Electrical Code covers energy management systems, and recent editions allow a system that limits the load to be used in the calculation in place of the raw connected total. Several product shapes do this. Some are smart loadcenters that monitor every breaker and shed the lowest priority circuit on demand. Others are single circuit controllers that drop the clothes dryer or the EV charger the instant the heat strips energize. One variety attaches at the meter and needs utility approval before it goes on.
The thermostat holds a cruder version of the same idea. Strip heat can be locked out above a chosen outdoor temperature, so the elements cannot energize on a 40 degree morning when the compressor has the house covered. That is a control setting rather than a listed device, and it will not change a code calculation, though it does change what your house draws across a winter.
Acceptance is the catch. Inspectors differ on how these devices get credited in a load calculation, so the electrician confirms with Prince George's County before the device becomes the plan rather than after the equipment is on site.
A Smaller Backup Heat Package
Backup heat sized to the real gap instead of the whole heating load is the cheapest move on this list, and it is the one skipped most often.
Balance point is the term that makes this make sense. It is the outdoor temperature at which the heat pump's output exactly equals the house's heat loss. Above that temperature the compressor carries the house alone. Below it, something has to supply the difference, and the difference is what the heat kit exists for.
Maryland winter design temperatures sit in the teens, a figure that comes out of the ASHRAE weather data designers size equipment against. Your house's heating load at that temperature comes from a Manual J calculation, the residential load calculation standard published by the Air Conditioning Contractors of America, which works room by room off real wall, window and infiltration numbers. The heat pump's capacity at that same temperature comes from the manufacturer's expanded performance table for the exact model, and ENERGY STAR's cold climate criteria hold certified models to performance measured at 5 degrees Fahrenheit.
Run it with round numbers. Suppose Manual J puts the design heating load at 36,000 Btu per hour and the published table for the quoted model shows 26,000 Btu per hour at 17 degrees. The gap is 10,000 Btu per hour, which is under 3 kilowatts of resistance heat, so a 5 kilowatt kit covers it with margin to spare. Go back to the table above. That is a 30 amp circuit instead of the 80 amp circuit a 15 kilowatt kit would have demanded, in the same house, for the same winter.
Honesty about the tradeoff belongs here, since it is the reason installers reach for the big kit. A heat package sized to the gap cannot heat the house by itself. If the compressor fails in January, emergency heat becomes partial heat until somebody repairs it, and in a hard cold snap the house may drift a few degrees below setpoint. Most homeowners who understand that still prefer the smaller kit, and anyone who does not want that exposure should hear what the larger one does to the panel.
Dual Fuel, Where No Strip Heat Exists
A conversion that keeps the existing gas furnace as its backup heat source has no electric heat package in it at all, and losing the heat package usually loses the electrical problem with it.
Dual fuel means a heat pump outside and the gas furnace already in the basement, sharing one duct system under one control. The heat pump handles everything above a switchover temperature the installer sets. Below that, the furnace takes over and the compressor stops. No strip heat gets installed anywhere in the system, because the furnace is doing the job those elements would otherwise do.
Count the circuits in that version. One new 240 volt feeder for the outdoor unit, its disconnect, and the furnace's existing 120 volt circuit left exactly where it is. Nothing else. Plenty of 100 amp houses pass a load calculation in this configuration without any panel work beyond adding a two pole breaker, which is the whole appeal.
What you give up is the reason this is a real choice rather than an obvious one. The gas meter stays, the fixed monthly gas charge stays, and the house has not gotten off gas. Dual fuel also depends on the furnace having years left in it, a heat exchanger in sound condition and venting that still works correctly once the equipment around it changes, which is a separate inspection and a separate conversation.
TerraStream Energy converts Maryland homes off gas and oil heat onto electric heat pumps, and that electrification work is the center of the business rather than a sideline. Which means the company has reason to tell you plainly when dual fuel genuinely fits a house, and when it is being used to avoid a hard conversation about the panel.
Sequencing the Electrical and Mechanical Scopes
Who Holds Which License
Panels, feeders and service upgrades belong to a licensed electrician, the heating and cooling scope belongs to the HVAC contractor, and in Maryland those are two different licenses held by two different people.
Maryland licenses heating and cooling contractors through the State Board of Heating, Ventilation, Air Conditioning and Refrigeration Contractors, and that license covers the equipment, the refrigerant circuit, the duct connections and the low voltage controls. Electrical work runs on a separate track. Master electrician licensing is administered at the county level across much of the state, and Prince George's County issues the electrical permit independently of the mechanical permit on the changeout. Two permits, two inspections, two trades signing for their own work.
An HVAC contractor who says he will take care of the panel is doing one of two things. Either he has an electrician he works with and can name, with that scope written into the proposal, or he is about to add a 60 amp breaker outside his license and hope the inspection goes quickly. Ask which, and ask for the electrician's name and license number.
The Order These Two Scopes Run In
Load calculation first, electrical work second, equipment third, and reversing that order is how a conversion becomes a house with no heat for a week in January.
The sequence that works has five steps, and each one feeds the next. A Manual J load calculation establishes the house's heating and cooling loads. Equipment selection follows, which fixes the model numbers and, more to the point here, the heat kit size. Your electrician then runs the Article 220 calculation using that kit's published electrical data and the utility's twelve month demand history, and returns either a pass or a scope. Electrical permit and electrical work come next, whether that is two breakers, a load management device or a full service upgrade. Only then does the mechanical permit get pulled and the changeout get scheduled.
Picture the version where nobody did that. Your old furnace is out and sitting in the driveway. A new air handler is set and piped, the lineset is brazed, and the electrician arrives to find a panel with no space for a 60 amp two pole breaker and a calculated load that already exceeded the service before the heat kit entered the picture. Nobody can energize the strips. That house runs on compressor only through a cold stretch while a panel change gets permitted, and the homeowner learns in the worst possible week that the 15 kilowatt kit was a choice somebody made without checking.
"The panel is the thing that most often changes the shape of one of these jobs, and I would much rather find that out standing in your basement in October than on a Tuesday in January with your old furnace already on my truck. Get the load calculation done, get the electrician's scope in writing, then we order equipment." Jake Mazzoccoli, Owner, TerraStream Energy
How TerraStream Energy Would Approach This
TerraStream Energy works across Maryland and takes Prince George's County first, which means these houses are familiar ground. Brick ranchers and split levels with a gas furnace in the basement, a condenser from a different decade outside, and an original panel in the laundry room.
A conversion starts with the two calculations, before any model number gets written down. TerraStream Energy runs the Manual J on your actual house, selects equipment against the loads it produces, and sizes the backup heat package to the gap above the balance point rather than to the full heating load, since that single decision does more to the electrical scope than anything else on the proposal. The panel gets read on that same visit. Main breaker rating, free spaces, which gas appliances are staying, whether a subpanel is worth using.
Panel work, feeders and service upgrades are an electrician's scope and TerraStream Energy does not perform them. What the company does is hand your electrician the exact air handler and heat kit model numbers with the manufacturer's published MCA and MOCP, so the Article 220 calculation runs on real figures before equipment is ordered and the electrical work gets scheduled ahead of the changeout instead of discovered during it. Duct modifications, air sealing and anything involving your water heater's venting belong to other trades, and the company will say so rather than quote them.
Incentives deserve a separate phone call of their own. Federal credit rules and state program terms change from year to year, so check current rules with the Maryland Energy Administration and confirm what applies to your project before you budget around it.
Call TerraStream Energy at 703-772-5970 or use the contact page to get a load calculation on the calendar. Bring the number off your main breaker when you call, along with a list of which appliances in the house still burn gas.
Frequently Asked Questions
Do I need a 200 amp panel to put a heat pump in my house?
No. A load calculation under Article 220 of the National Electrical Code decides it, and a 100 amp service in a gas heated house passes more often than homeowners expect, because a gas range, a gas water heater and a gas dryer keep the three largest electric loads out of the arithmetic. What usually tips it over is a large electric strip heat package. Size the backup heat to the real gap above the balance point, or keep the existing furnace as dual fuel backup, and many 100 amp services carry a heat pump with nothing more than a new two pole breaker.
Why does the electric backup heat matter more than the heat pump itself?
Resistance heat draws far more current than a compressor. One kilowatt of strip heat produces 3,412 Btu per hour and pulls about 4.2 amps at 240 volts, so a 10 kilowatt package draws 41.7 amps and lands on a 60 amp breaker once the code's 125 percent continuous load factor is applied. A residential heat pump compressor's minimum circuit ampacity commonly sits in the twenties. The heat package is therefore the larger number, and in a Maryland house the code counts the compressor and the strips together because they are arranged to run at the same time.
Who does the panel work, and does TerraStream Energy handle it?
A licensed electrician does the panel, the feeders and any service upgrade. TerraStream Energy performs the heating and cooling scope, which covers the equipment, the refrigerant circuit, the duct connections and the controls, and the company does not perform electrical work. Maryland licenses those trades separately, and Prince George's County issues the electrical permit independently of the mechanical permit. What TerraStream Energy provides is the exact air handler and heat kit model numbers with the manufacturer's published electrical data, so your electrician can run the load calculation before equipment is ordered.
What are my options if the load calculation comes back over the service rating?
Four. Upgrade the service, which raises the ceiling permanently and involves the utility and a county electrical permit. Install a listed energy management device that sheds a load when another one calls, which recent code editions allow in the calculation, subject to how your inspector credits it. Select a smaller backup heat package sized to the gap above the balance point instead of the whole heating load. Or keep the existing gas furnace as dual fuel backup, which removes the electric heat package from the project entirely and leaves only the outdoor unit's circuit to add.
What does a conversion add to my panel in circuits?
Two, in the usual case. A two pole 240 volt circuit to the outdoor heat pump, sized to the minimum circuit ampacity on its rating plate with a breaker no larger than the maximum overcurrent protection, plus a disconnecting means within sight of the unit. Then a feeder to the air handler, sized for whichever electric heat kit is installed, which ranges from a 30 amp circuit on a 5 kilowatt kit to 80 amps on a 15 kilowatt kit. The old gas furnace's 120 volt circuit cannot carry an air handler with strip heat in it.
Should I get the electrical work done before the equipment is installed?
Yes, and the order matters. Manual J first, then equipment selection that fixes the heat kit size, then the electrician's Article 220 calculation using that kit's published data and twelve months of demand history from the utility, then the electrical permit and the electrical work, and only then the changeout. Reverse it and the furnace comes out before anyone knows the panel has no room for a 60 amp breaker, which leaves the house on compressor only while a panel change gets permitted.